Monday October 3, 2011
All inspections for cassion drilling, building of cassion cages and placement of them into the holes were obtained from Soil Engineers, Structural Engineer, Deputy Inspector and City Inspector.
Concrete is scheduled to be poured on Tuesday 10/4/11.
Wednesday September 21, 2011
All 25 casion holes including Building and the retaining wall holes were drilled, completed and Soil Engineers approval obtained.